RECONDITIONING AND RECREATION OF THE CHANNEL 25 DE MAYO

Province: SAN JUAN
Town: May 25
Client: MINISTRY OF PRODUCTION AND ECONOMIC DEVELOPMENT PROVINCIAL AGRICULTURAL SERVICES PROGRAM (PROSAP)

Description:

Reconditioning and Regrowth of the 25 de Mayo canal – length 14.40 km to the 25 de Mayo neighborhood, all lined with concrete. Highway and Access Bridges. The main works of art along the canal are made up of a large number of highway bridges and access bridges to properties that cross it, as well as several footbridges and siphons that cross irrigation branches. In total, 10 pedestrian walkways, 12 highway bridges, 31 property access bridges, 6 aerial irrigation crossings and 28 siphons are located along the canal.

Duration: 15 Months
Date: November 2008

CONSTRUCTION OF PRIMARY AND SECONDARY IRRIGATION NETWORK OF THE 1st. And 2nd. SECTION

Province: SAN JUAN
Town: May 25
Client: Secretariat of Water Resources of San Juan

Description:

length approx. 75 Km. In primary and secondary sections – Land cleaning 73 Has. – Excavation not classified 170,000 m3 – Compacted embankment 520,000 m3 – Soil transport 2,539,000 Hmm3 and 16,076,400 Hmm3 – Excavation of the channel box in compacted embankment 123,700 m3 – Concrete in gral. for works of art and waterproofing of the channel 39,800 m3. – Construction of all works of art for access to properties, for distribution of liquids and for crossing streets.

Date: 1979-1984

CONSTRUCTION OF A CLOACAL LIQUID TREATMENT PLANT

Province: SAN JUAN
Location: Rawson
Client: National Entity of Water Works for Sanitation (ENHOSA)

Description: Construction of the Grid Chamber Sewage Liquid Treatment System, Parshall Gauge, Channels and Access Gate to Lagoon, Excavation, Embankment and Waterproofing of Lagoons, Interconnection Chamber and Exit Canal to the Agua Negra Stream.
Drilling of 350m of Depth for the Provision of Drinking Water to the Building Complex. Edilicio, Forestation and Irrigation Complex, Perimeter Roads. and Electric Power Network.

Duration: 32 Months
Date: March 2006

RUNNING AND DEEPENING OF THE "AGUA NEGRA" STREAM

Province: SAN JUAN
Location: Rawson – July 9
Client: Department of Hydraulics

Description:

Unclassified excavation, work of art, Placement of a 2.5m pipe as an intern under streets No. 14,11,10,8 and 5 with their corresponding protection mats.
Gabion construction of bottom jumps, Base construction – Stabilized sub-base, Bituminous Primer, placement of metal rails and vertical signage

Duration: 14 Months
Date: January 2006